Give the slab quantity a clear measurement basis.
A metric concrete example with separate volume, allowance and KRW material subtotal.
A uniform rectangular slab begins with length × width × thickness. Express all three dimensions in meters. A drawing thickness of 150 mm is 0.15 m; enter that converted value in the volume calculation.
Show volume and allowance separately
A 10 m × 8 m × 0.15 m slab measures 12 m³. An illustrative 5% allowance produces 12.60 m³. The geometric volume describes the measured slab; the allowance is a planning decision. It is not a prescribed waste rate or a design requirement.
Apply a quotation on the right basis
At an illustrative ₩100,000/m³, the concrete material subtotal is ₩1,260,000. This is not a Korean market average or a supplier offer. Confirm product specification, quotation validity, minimum order, delivery and separate services with the supplier.
Complete the work package
Reinforcement, formwork, labor, pumping, testing, equipment, delivery and tax are outside this material subtotal. Beams, steps, openings, drops and different slab thicknesses need separate measurement treatment.
At the same 12.60 m³, changing the example rate to ₩110,000/m³ makes the subtotal ₩1,386,000, a difference of ₩126,000. That is a sensitivity calculation, not a market forecast. Copy the reviewed inputs into TB manually.